Russell is on the verge of a major overhaul to its electric distribution system as the city gears up to launch a comprehensive reconstruction project. The project, led by the city electric department in collaboration with KMEA/Midstates and RMA Engineering, aims to bolster the reliability and efficiency of the local power infrastructure. The first construction phase is contracted to IES Electric, Holdredge, Nebraska.

This comprehensive reconstruction project includes rebuilding more than twelve electric distribution circuits.

Originally authorized by the city council in February 2022, the electric distribution rebuild project is set to commence with the first phase: the East Residential 1 and 2 circuits, which cover State Street to Wichita

Avenue and N. Fossil Street to Copeland Street. This initial phase, expected to span up to twelve months, will encompass the replacement of power poles, power lines, and transformers within the designated areas.

Following the completion of the East Residential circuits, the project will transition to the next phase, which will be North Residential 1 and 2 circuits, followed by additional circuits each year until completion.

The City of Russell has secured significant funding for the forthcoming project phases. A federal BRIC grant of $2,039,000 has been awarded for the North Residential 1 and 2 portion, complemented by an additional $339,000 allocation from the State of Kansas’ Build Kansas Fund.

IES will diligently mobilize resources throughout the project to ensure timely execution and minimal disruption to residents. Short power outages may be necessary during specific tasks, but advanced notice will be provided to affected customers. Notices will be distributed via door hangers and the city's Notify Me system, offering a 24-hour lead time for planned outages.

Residents can stay informed about project developments and outage schedules by signing up for the Notify Me system at www.russellcity.org. For inquiries regarding the electric distribution rebuild project, please get in touch with Dave Sturgeon, Electric Utility Director, at 785.483.7112.

This initiative underscores the Russell City Council’s commitment to modernizing its infrastructure and providing a dependable power supply for its residents. With the collaborative efforts of the city electric department, KMEA/Midstates, RMA engineering, and IES, the project is poised to achieve its objectives efficiently and effectively.